1Introduction & Account Setup
Overview, accessing ConduitNET, creating your MAGNET4WATER account.
Slide 3: Browse to: https://www.magnet4water.org/conduitnet
This site hosts the complete, integrated pipe network modeling, analysis, and visualization platform. The default interface environment is shown here.
Slide 4: Create an account: [Menu Bar] Credentials > Log In
Slide 5: Create New Account: [Menu Bar] Credential > Log In > Sign Up
You only need to create one account to access all the MAGNET4WATER Platforms (IGW-NET, StormNET, SwaNET ConduitNET and DataNET)
2Start a New Synthetic Project
Create a synthetic (non-geo-referenced) model — a "numerical sandbox" with no real-world map base.
Slide 6: Start a New Project: [Menu Bar] FILE > New Project
Use File menu to start a new project, save the model file, upload an existing model, and view saved model INP (input) files. For this tutorial, choose the Synthetic Model Type and click Submit. This will remove the background map from the display / Working Environment so the user can work within a “numerical sandbox”. Note: By default, ConduitNET models are map-based (or geo-referenced to real-world locations). In these types of models, pipe lengths can be auto-calculated and pipe elevations can be based on a Digital Elevation Model (DEM). A Quick Tutorial for GeoReferenced models is coming soon.
3Add Nodes: Reservoir, Junctions, Tank
Add and configure the network nodes — reservoir as source, junctions as demand points, tank as storage.
Slide 7: Add Reservoir: Nodes > Reservoirs > click, right click > Start Drawing
The cursor turns into a blue circle, indicating ‘Drawing Mode’ is active. Use a single-click to add the reservoir to the map display. *Note that if you hover the cursor over a node or link object, the Map Status hover field will indicate the node / link ID of that object.
Slide 8: Edit Reservoir: 1. Nodes > Reservoirs > click, right click > Stop Drawing 2. Nodes > Reservoirs > click, right click > Edit Reservoirs* *A single-click on any map object also launches its Editor menu.
Select the reservoir by its Reservoir ID (1 for this example). The total head in Reservoir 1 should be set to 700ft. DEM and DEM Offset are set to zero for synthetic model. Click ‘Save’ to finalize changes before exiting the Reservoir Data Editor (‘X’ button).
Slide 9: Add Junctions: Nodes > Junctions > click, right click > Start Drawing
Again, the cursor turns into a blue circle, indicating ‘Drawing Mode’ is active. Use a single-click to add the six junctions to the map display. Add the notes in the approximate locations indicated in the figure. Follow the correct order so that the Junction ID matches the network plan shown here and in slide 2*. *Note that, in principle, the IDs can be different from those used in the network plan, but it makes trickier to assign junction-specific attributes from the example.
Slide 10: Edit Junctions: 1. Nodes > Junctions > click, right click > Stop Drawing 2. Nodes > Junctions > click, right click > Edit Junctions
Slide 11: Edit Junctions (cont.): Reservoir Junctions Tank
Select the different junctions by their Junction ID (2-7 for this example) for attribute editing. The total head in Junction 2 should be set to 700ft. The Base Demand should be set to zero. Click ‘Save’ to finalize changes before selecting a new junction for editing: Junction 3, edit attributes, Save; Junction 4, edit, Save; and so on… After updating and saving all of the junctions, close the Junction Data Editor window (‘X’ button).
Slide 12: Add Tank: Nodes > Tanks > click, right click > Start Drawing
The cursor turns into a blue circle, indicating ‘Drawing Mode’ is active. 1. From the dropdown box, select Functional/Custom SU, 2. Click Start Drawing button and use a singleclick to add the tank to the map display.
Slide 13: Edit Tank: 1. Nodes > Tanks > click, right click > Stop Drawing 2. Nodes > Tanks > click, right click > Edit Tanks
Select the tank using the Tank ID (8 for this example). Assign a elevation of 830ft. Assign an initial water level of 3.5ft. Assign a minimum level of 0ft. Assign a maximum level of 20ft. Assign a diameter of 60ft. Click ‘Save’ to finalize the changes before closing the Tank Data Editor.
4Add Pipes & Pumps (Links)
Draw pipes connecting your nodes, define a pump curve, and add pumps to lift water into the tank.
Slide 14: Add Pipes: Links > Pipes > click, right click > Start Drawing
Again, the cursor turns into a blue circle, indicating ‘Drawing Mode’ is active. Click once on Junction 2 to snap the pipe’s starting position to it. A blue line will extend from the node as you move the cursor. Double click on Junction 3 to snap the pipe’s ending position to it. *Once a pipe is started (linked to the starting node), a single click only places a vertex for drawing purposes. The pipe is still “open” (not snapped to an end node). *At this time polylines are not supported. **A pipe must have a starting and ending node. “Bad” pipes are deleted from the map display. If you get a thin blue line this indicates the link was unsuccessful. When this happens click “Undo” on the map toolbar, or “Stop Drawing” and “Start Drawing” on the Link menu.
Continue adding pipes to the network in the order indicated here and on slide 2. *Do not use a pipe to link the reservoir to Junction 2. A pump will be used as a link between the reservoir and Junction 2.
Slide 16: Edit Pipes: 1. Links > Pipes > click, right click > Stop Drawing 2. Links > Pipes > click, right click > Edit Pipes
Select the different pipes by their Pipe ID (1-8 for this example) for attribute editing. The length of Pipe 1 should be set to 3000ft*. The diameter should be set to 14. The C-Factor (Roughness) should be set to 100. *Note that the pipe length is automatically calculated from the map, but this can always be overwritten with user-inputs. Click ‘Save’ to finalize changes before selecting a new pipe for editing: Pipe 2, edit attributes, Save; Pipe 3, edit, Save; and so on…
Slide 17: Edit/Define Pump Curve: Non-Physical Objects > Curves > click, right click > Edit Curves
Select the Pump Curve tab from the Curve Editor Window A pump curve ( Curve Id ‘1’ ) is automatically predefined.* Update Flow to 600 GPM and the Head to 150. The software will create a curve through this (pumping rate, head) data point to define the relationship between pumping rate and head in the pump object.**. Click “Save Curve” to finalize the changes. For one point curves the equation used by the software is of the form: ℎ= 𝑏−𝑎𝑄 2 Where h is the Head, Q is the Flow, and b and a are constants determined from the input point(s). *When additional pump curves are needed, click “Add New Curve” button, a new Curve Id (e.g. ‘2’) will appear in the “Curve Id” dropdown box. **Generally speaking, as flow increases, head decreases.
Slide 18: Add Pump Links > Pumps > click, right click > Start Drawing
Again, the cursor turns into a blue circle, indicating ‘Drawing Mode’ is active. Click once on Reservoir 1 to snap the pump’s starting position to it. A blue line will extend from the reservoir as you move the cursor. Double click on Junction 2 to snap the pipe’s ending position to it. *A pump must have a starting and ending node. “Bad” pumps are deleted from the map display. If you get a thin blue line this indicates the link was unsuccessful. When this happens click “Undo” on the map toolbar, or “Stop Drawing” and “Start Drawing” on the Link menu.